Our 100 year old church building has been replaced by a new building more suitable for its purpose. The demolition of the old building commenced on the 13th October 2009 and the new building was officially opened on the 4th October 2009.

 
 

The picture on the left shows what the church should look like when it is finished, provided that all goes according to plan. Click on the picture to see a bigger version.

At present the build programme is basically on schedule and it looks like the first meetings in the new building will be held in September 2009.

A programme of events is being planned around the opening of the new building which will give people the opportunity to visit the building itself, but more importantly to hear why we believe it is important to invest time and money in putting up such a building as this.

We believe that a building is simply a tool to be used to help people hear and accept the message of the Bible and then help them to grow in their faith.

   
   
 

The roof comes off (21st and 22nd October 2008)

   

 

   
   
   
   
   

Further progress, 26th October 2008

   
   
   

27th October 2008

   
   
   

4th November 2008

   
   
   
   

7th November 2008

   
   
   
   

25th November 2008- the foundations are dug and the concrete is being poured.

   
   
   
   

27th November. The foundations are left to set

   
   
   

   

10th December 2008 - the steelwork starts to go up.

   
   
   
   

11th December 2008 - the builder's aren't hanging about!

   
   
   
   

17th December 2008 - the blockwork has started

   
   
   
   

14th January 2009, floors are in, walls have commenced.

   
   
   
   

24th January 2009, the walls are further up

   
   
   
   

2nd February 2009 

   
   
   
   

11th February 2009 

   
   
   
   

5th March 2009 

   
   
   
   

13th March 2009  - the roof goes on

   
   
   
   

18th March 2009 

   
   
   
   

10th April 2009 

   
   
 

                  Click on the above picture to see a larger image

29th May 2009 

 

   

                   Inside the main hall (facing forward)

     Inside main hall, facing the balcony

30th June 2009 

   
   

Church exterior 8th August 2009                           

                        Main hall from balcony 8th August (click to expand)

   
   
   

                 Main hall, looking rearwards 8th August                       

                  Hallway, ground floor 8th August

   
   
   

                Interior rooms, ground floor 8th August                             

                     Upstairs room 8th August

   
   
   

4th September 2009 

   
   
   
                   4th September 2009                   
   
   
   
   
Hallway from upstairs
   
   
                          The inside of the main hall              The outside of the building - almost finished!
1st October 2009
 
   
   
5th October 2009
 

 

   